The E18 scheme had a fast track delivery of two years, officially opening on-time for traffic in March 2018.
This Norwegian major infrastructure project was completed within the agreed timescales despite the VVB project teams working through two severe winters, where temperatures in Larvik were often -10 deg for months at a time. To meet the contractual milestone objectives VVB worked closely with its supply chain; agreeing fixed price productivity targets for the key installations to drive the works for Lighting, Ventilation, ITS and associated cable containment.
As an RLA Consultant - I performed a three year secondment to Oslo for VVB Nordic in the role of CEO, and Operations Manager with direct responsibility for the scheme delivery and the reporting of KPI's to the UK Board.